How much does underpinning cost in Toronto?
Underpinning and basement-lowering permits in Toronto, priced from declared construction values — plus how long the permit takes, where the work concentrates, and what else lands in the same job.
The full spread, not an average
| Percentile | Declared value |
|---|---|
| P25 — smaller jobs | $50K |
| Median | $100K |
| P75 — larger jobs | $300K |
| Largest in sample | $2.0M |
1,361 permits with a declared value, trailing 36 months. Medians and quartiles only — one outlier can't move them.
How long the permit actually takes
Measured from the date the application was filed to the date the permit was issued, on permits that reached issue. It excludes the design and engineering time before filing, which is usually the longer half of the wait.
Is this market growing?
| Year applied | Permits | Median declared |
|---|---|---|
| 2024 | 478 | $100K |
| 2025 | 726 | $100K |
| 2026 · year to date | 818 | $90K |
Counts are primary permits only — the plumbing, drain and HVAC permits filed alongside the same job are excluded so one project counts once.
Concentration across the city
| District | Permits | Share | Median declared |
|---|---|---|---|
| West End | 789 | 39% | $100K |
| East York & East End | 718 | 36% | $85K |
| Downtown | 234 | 12% | $100K |
| Etobicoke | 165 | 8% | $100K |
| Scarborough | 71 | 4% | $65K |
| North York | 36 | 2% | $128K |
Grouped by the first two characters of the postal code, so these are broad districts rather than neighbourhoods. See the live map →
What else is in the same permit
| Residential alterations | 1,992 permits | 99% |
| Secondary suites | 124 permits | 6% |
| Multiplexes | 107 permits | 5% |
| Demolition | 67 permits | 3% |
Share of these permits that also carry each scope. This is why quotes vary so widely — the same word can describe a standalone job or one line inside a much larger renovation.
Why there is no $/SF figure here
We publish a per-square-foot rate only where floor area is what the price actually scales with. For this work the correlation between area and declared value is 0.56 — too weak for a rate to predict your project. Multiplying your floor area by a published $/SF number would produce a confident-looking figure that the underlying permits do not support, so we show the value distribution instead.
Why two of these quote differently
- Linear metres of wall underpinned and the depth of each pin — price is quoted per pin or per linear foot, and both scale with how far down you go.
- Soil conditions and water table — dewatering and shoring change the job entirely.
- Whether the scope includes a new slab, drainage and waterproofing (it usually does).
- Access: a semi-detached with no side entrance means every bucket comes out through the house.
- Bench footing instead of true underpinning — cheaper and faster, but it eats floor area, so the two are not interchangeable quotes for the same result.
Check it against the record
| Applied | Address | Declared value |
|---|---|---|
| Oct 2026 | 27 QUINCY CRES
Interior alteration of an existing single-family dwelling. The scope of work includes... |
$35,000 |
| Oct 2026 | 51 HALFORD AVE
Proposal for interior alterations, new exterior openings, underpinning, new basement... |
$750,000 |
| Sep 2026 | 1350 MOUNT PLEASANT RD
Underpinning of existing single family dwelling (67.4 linear m) |
$30,000 |
| Sep 2026 | 5 HIGHBOURNE RD
Proposed addition, interior alteration, underpinning, and new deck, to convert SRF to... |
$500,000 |
Where these numbers come from
Declared construction values on City of Toronto building permits (tier C), trailing
36 months, minimum 12 permits before a guide is published. A declared value is
what the applicant stated the work is worth — it can sit below final hard cost,
which is exactly why GROUND also publishes
awarded contract prices.
Underpinning is the most common way a basement second suite becomes legal, so these projects frequently overlap with suite permits. Every underpinning job needs a structural engineer's drawings before permit, and the declared values here include that design work.
Data: Open Government Licence — Toronto. Recomputed automatically as new
permits land; the figures above are current as of October 05, 2026.
Pricing a project like this?
The numbers above are the market. For your project specifically — your address, your scope — we'll read the comparables, flag the permits you'll need, and check any quote you've been given against real awarded prices.
Interior fit-outs · New houses · Laneway & garden suites · Additions · Garages · Second suites